Committee members discussed the possibility of water reservoir facilities in Rochester |
Hills. |
* Arcadis FPS, Inc., consulting firm, completed the original study in September of |
2002 which indicated the demand, fire flows and the size of the water mains. |
* Identify pressure in the existing water distribution system. |
* Identify ways to lower peaks. |
* Identify potential system improvements |
* Initial preliminary indications showed a savings in water purchase rates using water |
storage. |
* The water storage reservoirs provide storage of water purchased at low rate with |
distribution during high peak rate. |
* Based on information compiled, water storage facilities are economically feasible. |
* Detroit Water and Sewer Department ( DWSD) approves of the concept of water |
storage facilities in Rochester Hills. |
* Conclusions of study were recommendations to build two (2) - two million gallon tanks. |
* Total estimated construction costs $7.3 million. |
* Total estimated savings between five (5) and seven (7) years is $7.3 million. |
Committee discussed current water distribution system |
* Rochester Hills has a very complex water distribution system with 265 miles of water |
main. |
* There are nine (9) different pressure districts, two (2) pump stations and four (4) |
metering stations. |
* Rochester Hills serves a population of 70,000 with 22,000+ accounts. |
Committee discussed billing and rates. |
* Currently there is a three-stage billing. |
* Five factors are used for rate setting: |
* Base rate is the average daily usage of water. |
* Communities have no control over base rate. |
* Maximum day rate determined in summer when there is a great amount of water used |
. |
* Communities have some control over maximum day rate through water conservation |
measures. |
* Peak hour rate is determined in summer when there is a great amount of water used. |
* Communities have considerable control of peak hour usage. |
Committee discussed the need to validate the economic value of first study. |
* Identified flow patterns within the Rochester Hills water distribution system. |
* Rochester Hills System is fed from four (4) separate points from DWSD. |
* Most water flows from only two (2) points. |
* Confirm water storage facility size and location for maximum benefit. |
* Confirm with DWSD stability of their rates and rate structure (no guarantee). |
* DWSD Water Rate Division explained how rates are established and verbally |
concurred that Rochester Hill's water reservoirs would eliminate the peak hour demand |
factor, which would then reduce rates accordingly. |
* DWSD engineering group is comfortable with Rochester Hill's storage designs. |
* DWSD requires an assurance that there is no impact on DWSD facilities. |
* DWSD requires Rochester Hills re-evaluate using higher peaking factors or the factors |
used to get the maximum day and peak hour rates to account for any future impact. |
* Rochester Hills is in need of reallocating the feed points where water flows into the |
distribution system. |
* Water flow is significantly utilized on west side feed point. |
* Water flow is less utilized from east side feed point. |
* DWSD will not allow improvements to east side feed point because it would have a |
negative effect on other communities water flow. |
* DWSD data used was peak July - September of 2003 as follows: |
* The distribution from the four (4) connections have evened out |
* The distribution is slightly better during peak flow than in low flow or |
* The supply pressure is often below pressure reducing valve settings. |
* Installing water reservoirs will resolve some of the pressure concerns. |
* Placing full control valves on each feed point gives Rochester Hills control over how |
much water they purchase from DWSD by not allowing the community to go above the |
maximum day rate. |
* Water would then be drawn out of the water storage facilities. |
* Arcadis FPS, Inc. system would monitor valves. |
* Over-ride ability in place on control valves in case of emergency. |
* Over-ride ability creates a risk of using peak hour rate. |
* DWSD determines our rate based on how Rochester Hills peak hour rate corresponds |
with Detroit's peak hour rate. |
* DWSD bases its rates on peak hour usage annually and the rates remain the same |
throughout the year. |
* Rochester Hills and DWSD did not have the same peak hours last year. |
* DWSD takes into effect the cost of power, pumps, and horsepower into deriving costs. |
* Annual cost basis with the water reservoirs is $650,000. |
* Annual cost basis without the water reservoirs is $2.1 million. |
Committee members discussed costs for water storage facilities. |
* Ground level water storage costs the least to install. |
* Elevated water reservoirs are more than double in cost. |
* Below ground water reservoirs involve added costs. |
* Water reservoirs should be located close to major feed lines to avoid additional piping |
costs. |
* Size determined at final design phase based on needs. |
* Water storage variations in capacities do not substantially change the cost. |
* Traditional security has been included in the estimated costs, such as, fencing, locks, |
and cameras. |
* National Industrial Tank dimensions used: |
* Concrete circular tank - 25 feet in height and 80 feet across holds two |
* Life cycle of a tank is estimated at fifty (50) years. |
* Other communities with water storage facilities: |
* South County Water (near Monroe County) |
* Others in North Carolina |
Committee members discussed security. |
* Arcadis FPS, Inc. system based on three (3) factors: |
* Deter by fence or camera |
* Detect by using gate switches on access ports that alert Arcadis |
* Response of Arcadis FPS, Inc. system tied into dispatch. |
Committee members discussed worst-case scenarios. |
* Roughly 600,000 gallons for residents and 600,000 gallons for fire flow. |
* Fire flow based on 3500 gallons per minute for three (3) hours. |
* Fire Chief confirmed Rochester Hills fire flow has never been close to that. |
* insurance that Rochester Hills will not hit peak hour rate. |
* total tank drainage would peak late in the day. |
Current comparable water rates: Detroit Wholesale vs. City of Rochester Hills |
Rankings from the lowest to the highest. |
* Rochester Hills ranked 109th out of 121 communities when comparing the |
* Rochester Hills ranked 42nd out of 114 communities when comparing the |
cost of maintenance and operations |
* Rochester Hills ranked 75th out of 114 when comparing the total charge to |
* Rochester Hills ranked 22nd out of 114 communities when comparing the |
percentage added to the DWSD charge |
* Rochester Hills had the 22nd lowest mark up percentage on last year. |
* Average mark up of a water customer is 125% |
* Rochester Hills is at 57% for 2004 (53% in 2003) |
* City of Detroit survey illustrates where Rochester Hills stands compared to 85 other |
communities. |
* In 2004, Rochester Hills is at 36th lowest (28th in 2003). |
* Average mark up of a sewer customer is 155%. |
* DWSD will reduce rates after Rochester Hills goes through a peak summer season to |
demonstrate to DWSD that: |
* the water reservoir is being managed correctly. |
* Rochester Hills is not having peak time corresponding with Detroit peak |
Dan Casey, Economic Development Manager, reviewed the draft Tax Abatement Policy |
noting the following: |
* Tax Abatement Program is regulated by Public Act 198 as amended in 2000 |
* Amendment now includes high technology and life science companies and removed |
the approval of the local community to approve a company's transfer to another |
community |
* Tax abatements are a tool that provide fifty-percent (50%) tax break on real and |
personal property for new investment in the community |
* Two factors are evaluated when looking at tax abatements: new investment and new |
jobs that result from the project |
* The globalization of the economy has resulted in competition of all levels of business |
as well as in government and Rochester Hills is competition with other cities, regions, |
states and countries for projects |
* The number of approval years legally allowed is different for real property and |
personal property |
* A substantial investment or a significant amount of new jobs in the community is |
required in order to qualify for the maximum of twelve (12) years. |
* Tax abatement programs assist in providing stability to a local economy for eligible |
companies who have applied and have been granted abatements by: |
* Providing additional workers |
* Retaining workers in a community |
* Increasing jobs within a community |
* Increasing the tax base within a community |
* Strengthening the company |
* Prior to the policy change on abatements, Rochester Hills approved forty-three (43) |
abatements from 1996-1997 |
* Since policy change, Rochester Hills has approved two (2) abatements |
* Currently the policy is that Rochester Hills does not give abatements |
* In attempt to further diversity the State's economy and to continue to convert it to a |
technology base or technology led economy to help soften the blow when automotive |
industries are struggling, the Governor established the tri-corrdior initiative which |
includes such things as the development of the Smart Zone Program, the Life Sciences |
Corridor, and energy initiatives |
* The State has provided some form of incentive to promote initiatives; however unlike |
other communities who established incentives using PA198, when Rochester Hills |
established its SmartZone, it did not provide an incentive program to support it |
* Draft policy changes include: |
* Attract companies and facilities engaging in advance manufacturing and |
* Reduce property taxes as an obstacle for development of problem |
* Place greater emphasis on retention and explansion of existing |
* Use it as a door to attract new companies |
* Problem with current policy is that while it does promote the use of this tool for |
companies who are transfering into Rochester Hills, it does not provide an incentive |
program to support it. |
* Several companies have chosen to locate in other communities other than Rochester |
Hills because of tax abatements. |
* Changes to policy will allow Rochester Hills to compete on a level playing field with |
other Michigan communities. |
Chairperson Hill suggested that CDV and Financial Services continue to review this |
matter at future meetings prior to presenting it to City Council. |
* Plante Moran will increase financial auditing cost for 2003 from $5000 - $7000 due to |
changes in required standards that include: |
* Requirement to look more closely at city contracts exceeding $400,000 for |
* Requirement to make inquiries of employees who may have knowledge of |
* Refunding that occurred this year saved the city $153,000. |
Roger Rousse, Director of Public Services, reported that City Staff discussed local Road |
Reconstruction with 120 representatives from the community to obtain input. |
* Community representatives had no objections to a millage. |
* Everyone in agreement that more money is needed. |
Mr. Rousse reviewed the City's history with millage questions noting the following: |
* There have been nine (9) millages for roads since 1980 |
* The following two (2) passed: |
*1980 - for five (5) years for $500,000 |
*1986 - for ten (10) years for $1,000,000 |
* The other seven (7) millage proposals failed. |
* Three (3) mills over five (5) years would generate $45 million. |
* A five (5) year millage would prevent a change of projections on pavement |
management system. |
* Past millage was for ten (10) years. |
* A five (5) year millage at $52 million would eliminate the need for three (3) millages |
after that. |
* A five (5) year millage renews with less millages on it to maintain |
* Committee member suggested calling it "residential street funding" instead of "road |
funding". |
* Committee members questioned feasibility for possible placement of millage on |
November ballot. |
Committee members discussed promoting community awareness of road fund shortage |
including the following: |
* Committee is in agreement with getting the information out to the residents |
* Staff will submit ten (10) articles to be be published in the Hills Herald |
* Committee members have volunteered to speak at subdivision association meetings. |
* Create a council of homeowner association presidents or representatives who can |
then share the information at local gatherings. |
Committee members discussed effects of budget shortage including the following points: |
* Local Fund budget could be reduced by $2 million. |
* Possible General Fund transfer to offset the $2 million shortage. |
* Affects operations and employees funded through local fund resulting in possible |
layoffs |
* Current Local Roads Fund balance is $800,000. |
* Three projects total cost of $700,000 are already committed by the City. |
* Chloride/grading project - $250,000 |
* New Love Lane project - $100,000 |
* Hillview SAD project - $350,000 |
Committee discussed the plan for road project and proposed millage questions. |
* Currently costs are at $52 million for replacing concrete with concrete |
* Costs $1.2 million to replace one (1) mile of concrete |
* There are forty-four (44) miles of concrete road. |
* Costs $900,000 to replace one (1) mile with asphalt. |
* Committee in agreement to "firm up" the plan, numbers, marketing, presentation, time |
frame |
* November ballot is feasible if an inside group or outside group marketed the program |
* Prior road millage took over one (1) year to plan |
* Committee concerned with school issues being put on the ballot at the same time |
* Committee suggested presenting plan to the Mayor and City Council |
* Committee concurred that the City needs to approach millage from perspective of |
homeowners and how it will benefit them. |