| Mr. Davis commented that MDOT has two walls that will be constructed, with |
|
| the remaining ten currently lumped together; however, he envisioned at the end |
|
| of the committee’s ranking process that perhaps one or two additional wall |
|
| projects would be considered for the CIP. He pointed out that currently, the ten |
|
| unfunded walls were submitted as a single project for the CIP at an approximate |
|
| cost of $14 million. He explained that there is a similar ranking process through |
|
| the CIP and noted that the total wall project ranked lower than the walls that were |
|
| approved because the two walls to be constructed have funding sources and |
|
| are to some extent mandated because the City receives Act 51 dollars. He |
|
| noted that the CIP ranking process allocates extra points because of those |
|
| funding conditions and mandates. |
|