| bring the city up to date. A letter was then sent to the residents stating that |
|
| there was information at the Rochester Hills Public Library and Rochester |
|
| Hills Municipal Offices. So far, they have not been advised of what has |
|
| been going on since the public hearing. He said a meeting was held a |
|
| couple of days ago with the city Engineering Department, Pat Goodwin and |
|
| himself. He said they discussed how they were going to cover this site. In |
|
| the meantime, they will continue monitoring the water to see if there is any |
|
| pollution down at the bottom. They will be doing some geo-probing after |
|
| they put the cover on. He raised the question at the meeting that if they do |
|
| geo-probe testing on it that they would be puncturing the cap. They |
|
| responded that it is possible to plug the hole that they make. It's not likely |
|
| that they will start work on this site until about the middle of 1996. They |
|
| have started to haul in fill to build the cap and the fill is coming from the |
|
| development at Mound & M-59. The city put a stop work order on it |
|
| because they didn't provide the plans and other required information. The |
|
| day following the stop work order, they posted a $10,000 cash bond. |
|