CALL TO ORDER
Chairperson Eric Kaiser called the Regular Meeting to order at ‎7‎:‎30 ‎p‎.‎m‎. ‎in ‎
the Auditorium‎.‎
ROLL CALL
Present PC‎:    ‎Chairperson Eric Kaiser‎
                          William Boswell‎
                          Paul Corneliussen‎
                         John Gaber‎
                         Greg Hooper‎
                         Leah Potere  ‎(‎enter ‎7‎:‎33 ‎p‎.‎m‎.)‎
                         Christian Ramanauskas‎
                         James Rosen‎
                         Audrey Ruggiero ‎(‎enter ‎7‎:‎45 ‎p‎.‎m‎.)‎
 
Absent PC‎:     ‎None‎
 
Quorum present‎
 
Also present‎:   ‎Patricia Goodwin, Planning Director‎
                         Deborah Millhouse, Deputy Director, Planning‎
                         Kenneth Snell, Mayor‎
                         Susanne Vergeldt, Recording Secretary‎
APPROVAL OF MINUTES
2000-1952
May ‎18‎, ‎1999 ‎Regular Meeting‎
 MOTION‎ by Ramanauskas, seconded by Corneliussen, that the Minutes ‎
 dated May ‎18‎, ‎1999 ‎be accepted as printed‎.‎
 
 Ayes‎:‎     All‎
 Nays‎:‎     None‎
 Absent‎:‎     Potere, Ruggiero   ‎MOTION CARRIED‎.‎
 
Approved
 
COMMUNICATIONS
 A‎.‎     Planning & Zoning News, May ‎1999‎
 B‎.‎     Notice of SPECIAL Planning Commission Meeting on June ‎29‎, ‎1999‎
 
 
DISCUSSION
2000-1953
2000 ‎Capital Improvement Plan ‎(‎CIP‎) ‎Preview‎
(‎Ref‎. ‎2000‎-‎2005 ‎Capital Improvement Plan Preview dated June ‎1‎, ‎1999 ‎prepared by ‎
the City of Rochester Hills Fiscal Team, and ‎2000‎-‎2005 ‎Capital Improvement Project ‎
Book dated May ‎1999 ‎prepared for the City of Rochester Hills CIP Policy Team ‎
have been placed on file and by reference become part of the record hereof‎.)‎
 
Ms‎. ‎Goodwin explained that the subject presentation is intended as a very informal ‎
discussion meeting‎.  ‎She acknowledged the presence of Mayor Snell who was present ‎
to provide the Fiscal Team's overview‎.  ‎Ms‎. ‎Goodwin reviewed that Municipal ‎
Planning Act ‎285 ‎discusses the capital improvement plan as a further implementation ‎
tool associated with the master plan or comprehensive plan and is one of the duties of ‎
the Planning Commission‎.  ‎The City has not had a formal capital improvement plan ‎
until the last three years; the first plan was adopted in ‎1998‎.  ‎Rochester Hills has been ‎
a city since ‎1985‎, so it is a fairly significant document for the city‎.  ‎
 
Ms‎. ‎Goodwin gave an overview of changes since the ‎1999 ‎CIP and gave an update ‎
of projects scheduled for completion in ‎1999 ‎-- ‎Adams‎/‎Dutton traffic signal, Auburn ‎
Technology Drive traffic signal, Dequindre‎/‎Hamlin traffic signal, Brewster Road ‎
rehabilitation, Drexelgate rehabilitation, Barclay‎/‎Hampton control beacon, type‎-‎deco ‎
character generator, feasibility study for remaining parcels, supervisory control and ‎
data acquisition ‎(‎SCADA‎)‎, Bassett‎-‎Smith watermain replacement, Martin Farms ‎
watermain replacement, and building needs assessment study‎.  ‎All major and local ‎
road projects under way are continuing in ‎1999‎.  ‎Ms‎. ‎Goodwin acknowledged ‎
Planning Commission Subcommittee Members Rosen and Boswell as members of the ‎
policy team‎.  ‎Ms‎. ‎Goodwin described the CIP Project Book which includes all the ‎
individual project submittal application forms as well as the evaluation criteria used by ‎
the city departments in their choice of projects to submit‎.  ‎These sheets were used to ‎
create the spreadsheet database found in the Preview book‎.  ‎Ms‎. ‎Goodwin ‎
distributed the ‎1999‎-‎2004 ‎CIP Review sheet listing ‎1999 ‎CIP projects completed; ‎
projects under review from the ‎1999 ‎CIP; project changes from the ‎1999 ‎CIP; start ‎
dates postponed during the ‎1999 ‎budget process by Council, Administration and ‎
Y‎2‎K; and projects withdrawn from the CIP‎. ‎
 
Ms‎. ‎Goodwin drew attention to the GIS map in the front of the Preview book which ‎
quantifies all projects contained in the book‎.  ‎The map includes local road projects, ‎
major road projects, park projects, and drain projects‎.  ‎The only projects not on the ‎
map are internal service projects‎.‎
 
     [ ‎Enter Ruggiero ‎7:45‎ p‎.‎m‎. ]‎
 
Mayor Snell explained that several capital projects that had been originally set in the ‎
CIP for ‎2001 ‎were pulled forward into ‎1999 ‎funding by City Council‎.  ‎Two of those ‎
projects were bringing water into the City Cemetery, and the Bloomer Park Stone ‎
Shelter building upgrade‎.  ‎The stone shelter is not being fully funded in ‎1999‎, so it will ‎
appear in subsequent years‎.  ‎Mayor Snell informed the commissioners that Oakland ‎
University is considering a conference center with a hotel, a performing arts center, ‎
and an ice arena‎. ‎Even though the City of Rochester is also building an ice arena, there ‎
may still be a call for one in Rochester Hills‎. ‎The ice arena in Rochester will have ‎3 ‎
sheet capability‎.  ‎Ms‎. ‎Goodwin added that the city's recreation plan will be up for ‎
review next year‎.  ‎If it is of interest to the Planning Commission, Mayor Snell stated ‎
that the ability to update the recreation plan will depend somewhat on the priorities ‎
and funding‎.  ‎City Council has conducted initial discussions but it has not yet been ‎
discussed in detail, nor has it been decided that it will be in the ‎2000 ‎budget‎.  ‎If the ‎
Planning Commission believes it should be supported, that may be a position the ‎
Planning Commission would like to take‎.‎
 
Ms‎. ‎Goodwin pointed out the overall formatting of the book for the benefit of new ‎
Planning Commission members‎.  ‎Ms‎. ‎Goodwin distributed Enhancements to the ‎
Capital Improvement Program for Fiscal Year ‎2000‎.  ‎Ms‎. ‎Goodwin explained the ‎
continuity between the Master Land Use Plan, the Master Transportation Plan, and ‎
the CIP‎.  ‎Putting the plan together crosses department lines and gives staff an ‎
awareness of what other departments are doing‎.  ‎Ms‎. ‎Goodwin suggested that ‎
commissioners review the recommended listing of policies and goals‎. ‎Ms‎. ‎Goodwin ‎
drew attention to the Policy Team Recommendations sheet in the Preview Book, ‎
located three sheets in front of the spreadsheet‎.  ‎Mayor Snell added an intangible goal ‎
reinforced with the Mayor's Exchange with Sterling Heights is a trust factor when ‎
residents can see that there is actually a plan for something to be done‎.  ‎Although any ‎
specific project may not happen this year, residents will know that it is on the list to be ‎
done in a certain time frame‎.  ‎Sterling Heights has found that, by diligently following ‎
their CIP document, they are able to demonstrate to people that a project is in the ‎
pipeline and that it will be completed‎.  ‎People are more likely to become more patient ‎
to wait their turn‎.  ‎The Mayor believed the city is building that trust and it will become ‎
apparent in succeeding years‎.   ‎The Chair added that trust is also accomplished ‎
between the Planning Commission and city administration‎.‎
 
For the benefit of the new Planning Commission members the Chair explained how to ‎
read the CIP spreadsheets and how to reference a project in the text‎.  ‎The Chair ‎
explained that the timing of some of the projects has been determined as long ago as ‎
10 ‎years because of funding availability and funding requirements‎.  ‎The timetable for ‎
some projects is determined by preexisting factors and long before projects reach the ‎
Planning Commission‎.  ‎The Chair referenced project MR‎-‎06 ‎on the spreadsheet and ‎
its cross‎-‎reference on Page ‎15‎.  ‎Information displayed includes the total cost, the ‎
city's share of the cost by percentage, the city cost in dollars, and an indication that the ‎
project is a tri‎-‎party funding by Road Commission for Oakland County, Oakland ‎
County Board of Commissioners, and the City‎.  ‎The Chair emphasized that the ‎
Planning Commission does not have to accept everything in the CIP‎.‎
 
Mayor Snell explained that, if all of the listed projects were to be funded to the levels ‎
shown, and if all of the listed projects were to be done, the city's cost would be ‎
$‎18‎,‎200‎,‎000‎, with an additional $‎26‎,‎310‎,‎000 ‎from other sources‎.‎
 
Ms‎. ‎Goodwin directed commissioners' attention to the Support and Role Identification ‎
page which describes the members and roles of the Project Team, Administrative ‎
Team, and the Public Relations Team‎.  ‎The Policy Team reviews the policy, develops ‎
the project rating and weighting criteria, rates and weights project applications, ‎
reviews funding options and presents the six‎-‎year recommendation to the ‎
Administrative Team‎.  ‎The Administrative Team reviews the Policy Team ‎
recommendation and develops a consensus for the projects to be brought forward in ‎
the six‎-‎year CIP, brings its recommendation forward to the Planning Commission ‎
Workshop and presents the CIP at the Planning Commission Public Hearing‎.  ‎The ‎
Public Relations Team prepares press releases, information packets, and the draft and ‎
final Capital Improvement Plan document‎.  ‎The Planning Commission's role is to work ‎
with the Policy Team during the plan development, conduct workshops, review the ‎
Administrative Team's recommendation, receive public input, conduct public hearings, ‎
adopt the plan, and request City Council to incorporate funding for the first year ‎
projects into the Budget Plan‎.  ‎The City Council incorporates the first year of the plan ‎
into the Budget Plan as part of the annual budget process in accordance with the City ‎
Charter and state law‎.  ‎Residents are encouraged to participate in plan development ‎
by working with the various Boards and Commissions, at the Planning Commission ‎
workshops, the Planning Commission public hearings and at City Council's budget ‎
workshops and public hearings‎.  ‎As always, communication is open between the ‎
residents, Council representatives, Planning Commission representatives and staff‎.‎
 
Ms‎. ‎Goodwin added that while the adopted plan may call for $‎18 ‎million, City ‎
Council must factor in the capital projects with all the other funding needs for the city, ‎
and really has a tough job deciding what will and will not be funded‎.‎
 
Continuing, Ms‎. ‎Goodwin pointed out the important Process Flow Chart‎.  ‎One of the ‎
key considerations of the Planning Commission was how public participation would ‎
flow into the CIP process‎.  ‎Public participation is overriding both at the front end as ‎
well as at the level where plans are submitted for approval and adoption‎.  ‎Public ‎
participation ideally comes in through all the policy documents such as the Master ‎
Land Use Plan, Master Transportation Plan, Master Recreation Plan, Local Road ‎
Improvement Plan, Pathway Plan, Storm Water Management Plan, the Local ‎
Development Finance Authority Plan, and the Water and Sewer Master Plan‎.  ‎There ‎
is room for public participation within each of these plans‎.  ‎These translate into actual ‎
projects‎.  ‎One of the key evaluation criteria is whether or not a project is consistent ‎
with one of these plans‎.  ‎If a project is not in one of these plans, it receives ‎20 ‎fewer ‎
points ‎-- ‎with the exception of internal service projects which are evaluated differently‎.‎
 
Member Rosen discussed the Needs Assessment Form‎.  ‎Projects are categorized into ‎
various project groups such as MR, Major Roads; LR, Local Roads; PK, Parks‎.  ‎It is ‎
difficult to compare ratings across these categories‎. ‎For example, a Major Road ‎
project rated ‎100 ‎would not directly compare with a Parks project rated ‎101‎.  ‎There ‎
is a difference that is not quantifiable‎. ‎Referring back to the Process Flow Chart, ‎
Member Rosen explained that the easiest way to explain this to the public is to ‎
recognize that the CIP is a compilation of projects that can be done‎.  ‎The Policy ‎
Documents are what we wish to do; the Projects are what staff wants to do; and then ‎
City Council funds what will actually happen‎.  ‎A change from last year's CIP was to ‎
include a way of tracking the progress of projects so they aren't forgotten or lost in ‎
succeeding years‎.  ‎
 
Ms‎. ‎Goodwin explained the process used by the project submitter utilizing sample ‎
forms in the CIP book‎.  ‎The project submitter completed Form ‎1 ‎(‎Individual Project ‎
Proposal Description‎)‎, ‎
Form ‎2 ‎(‎Project Summary‎)‎, and Form ‎3 ‎(‎Equipment‎) ‎which were then used as the ‎
basis for the Needs Assessment Form‎.   ‎The project submitter also ranked the ‎
projects‎.‎
 
Member Rosen explained the rating process from the Needs Assessment Form‎.  ‎After ‎
projects were submitted by each city department, each policy team member rated the ‎
projects themselves using the Score Range‎.  ‎The Score Range was then multiplied by ‎
the Weight to arrive at the Total Points‎.  ‎Member Rosen traced several projects ‎
through the process to illustrate the rating system‎.   ‎Ratings are ongoing once ‎
established, absent some emergency or unexpected contingency or change in ‎
circumstance‎.   ‎
 
Member Gaber stated that part of the purpose of the CIP document is to create some ‎
type of standard or plan which is to be followed and implemented year in and year ‎
out‎.  ‎Certainly priorities can change from year to year‎.  ‎But if Council had the ‎
opportunity to just ‎"‎cherry‎-‎pick‎" ‎projects and decide to fund only certain projects, ‎
then the document would lose credibility as a plan‎.   ‎You need some consistency from ‎
year to year‎. ‎
 
Ms‎. ‎Goodwin read the Policy Team Recommendation‎.  ‎It is recognized that several ‎
projects are components of strategic planning, and they should be postponed ‎
one year until the visioning program is complete and the community has come ‎
together to set the direction for the future‎.  ‎It has been established by the Mayor ‎
that the year ‎2000 ‎will be a ‎"‎time for completion‎" ‎for the many projects ‎
currently under way‎.  ‎Based on these premises, the following proposal is ‎
recommended‎: ‎The need for local road improvement is recognized and ‎
reconciling the gap between need and lack of funding source must be moved to ‎
the forefront; All major road projects that are currently under way should ‎
continue until they are concluded; All internal service projects to improve ‎
customer service should continue; Priority projects with available funding ‎
should be advanced‎."‎
 
Mayor Snell explained in the previous two years the Administrative Team ‎-- ‎consisting ‎
of Assistant to the Mayor, Financial Administrator and the Mayor ‎-- ‎had presented a ‎
recommendation to the Planning Commission of what it believed the CIP needed to ‎
contain as projects for each of the given years‎.  ‎Based on their experience to date, the ‎
Administrative Team this year is not formally recommending projects as needing to be ‎
funded in the years presented‎.  ‎The reason is that the Administrative Team is also the ‎
management Budget Team and will make the final decision on what will be placed in ‎
the proposed budget to City Council‎.  ‎The Administrative Team did not want to send ‎
a mixed message to City Council by recommending projects to the Planning ‎
Commission for certain years and then telling City Council something different‎.  ‎
Instead, the Administrative Team is sending an endorsement of proposed policies ‎
recommended by the Policy Team‎.  ‎In the actual budget documentation to City ‎
Council will be the final recommendation on actual projects for funding‎.  ‎Some of ‎
those may not be based on the same criteria in the CIP, but that is part of the process‎.  ‎
The CIP is not an inflexible document; the CIP is a planning document‎.  ‎
 
Mayor Snell clarified that project MR‎-‎04 ‎on Page ‎15 ‎reflects only a two‎-‎lane ‎
boulevard, even though the Major Thoroughfare Plan describes Hamlin Road from ‎
Livernois to Rochester Road as a four‎-‎lane boulevard‎.‎
 
The Chair advised the Planning Commissioners to be prepared for a full discussion of ‎
the CIP at the Public Hearing scheduled for June ‎15‎, ‎1999‎.‎
 
Ms‎. ‎Goodwin reviewed how the dollar amounts are set for the projects on the ‎
spreadsheets‎.  ‎A project cost is based on a variety of elements‎.  ‎A road project, for ‎
example, would involve preliminary engineering, right‎-‎of‎-‎way acquisition, actual ‎
construction, all of which are required to be done in a certain sequence‎.  ‎Each activity ‎
is costed out and spread over the amount of time required for its completion‎.  ‎Ms‎. ‎
Goodwin tracked Project MR‎-‎01‎, Crooks Road ‎(‎Auburn to Hamlin‎) ‎and pointed out ‎
that the cost to date of $‎1‎.‎1 ‎million reflects engineering and administrative costs since ‎
no construction has occurred and no rights‎-‎of‎-‎way have been acquired yet‎.  ‎For ‎
projects that have no set schedule and no identified funding source, such as Project ‎
PK‎-‎01‎A, Bloomer Park Stone Shelter, Mayor Snell explained that the cost to date ‎
includes initial professional services to prepare the documents and blueprints‎.  ‎The ‎
balance of the costs reflect an estimate of what the project should cost over two ‎
years‎.  ‎Sometimes the dollars are arbitrary because no definite plans exist yet‎.  ‎
 
Mayor Snell added that in the past the city has budgeted on dollars, not on resources, ‎
and has not thought in terms of multi‎-‎year projects‎.  ‎The CIP is really the first public ‎
presentation for the benefit of the residents as well as the Planning Commission and ‎
City Council and staff of what it really takes to accomplish a project that sounds ‎
simple‎.  ‎It should reduce the frustration endured by city staff as a result of not realizing ‎
why a certain project was not completed in a year‎’‎s time and not having adequate ‎
staff to tackle additional projects‎.  ‎City staff is in the process of project budgeting and ‎
action planning of all documents to get a better sense of what it takes to complete a ‎
project‎.  ‎One of the things included as part of the Year ‎2000 ‎budget discussions is to ‎
present an allocation of staff resources so that an overexpectation of available ‎
resources can be avoided‎.  ‎Compared to other cities Rochester Hills is significantly ‎
understaffed, and people need to recognize the limitations on our abilities to perform ‎
projects‎.  ‎In the past a project was budgeted only for a given year, and often there ‎
was no guarantee that there would be funding available to finish a project‎.  ‎They are ‎
beginning to look at the total cost of a project and encumber that and carry it forward ‎
from year to year‎.‎
 
Ms‎. ‎Goodwin stated that all the projects in the proposed Master Land Use Plan ‎
Update will be included in the ‎2001 ‎CIP‎.‎
 
Ms‎. ‎Goodwin added that another aspect of cost is operating and maintenance‎.  ‎The ‎
Transportation Plan discusses four‎-‎lane boulevards as the preference for major roads, ‎
and the cost of creating a landscaped boulevard that can be maintained with irrigation ‎
needs to be incorporated into the cost estimate‎.  ‎Irrigation has not been included in the ‎
cost estimates‎.‎
 
Member Gaber, noticed a primary change in the format of the spreadsheet over last ‎
year and found the change cumbersome and more difficult to use‎.  ‎Last year‎’‎s format ‎
provided more information and was much more readable‎.  ‎There appear to be more ‎
categories this year and more items‎.  ‎The Chair generally agreed‎.  ‎Member Gaber ‎
would like to see how much of an allocated funding source is available and how much ‎
needs to be supplemented from the general fund or some other place‎. ‎
 
Mayor Snell and commissioners discussed whether projects should be listed in the ‎
CIP even though no funding source has been identified, whether there is uncertainty on ‎
the part of some individuals about whether or not a project should be considered, or ‎
whether a project should be included when the funding source disappears‎.  ‎If these ‎
uncertain projects were included in the CIP, they could be tracked and would not ‎
have to be rethought of in the future‎.  ‎If there is no timetable identified for a specific ‎
project, perhaps it should not be included in the CIP, such as the community ‎
recreation center‎.  ‎However, the purpose of the CIP is to track such projects‎.‎
 
Member Hooper understood correctly that the Capital Improvement Project Book ‎
prepared for the CIP Policy Team and dated May ‎1999 ‎does not go with the CIP ‎
when it is adopted‎.  ‎It was prepared for information purposes‎.‎
 
Member Hooper and Mayor Snell discussed aspects of Local Roads funding and the ‎
fact that it is not as structured as the Major Roads category‎.  ‎Mayor Snell explained ‎
that the $‎6‎.‎6 ‎million shown on the spreadsheet for the Local Road Improvement Plan ‎
represents the estimated amount needed each year to implement the plan‎.  ‎City ‎
Council has not made any decisions regarding the amount of money that will be ‎
dedicated to local roads‎.  ‎Major roads are funded from a couple sources by ‎
deliberate policy decisions‎.  ‎As local roads are, major roads are also funded from the ‎
gas and weight tax but to a significantly higher amount than local roads‎.  ‎A half‎-‎mill has ‎
been dedicated by Council‎’‎s budgeting policy for major roads each year, so there is ‎
an additional amount of money for major roads‎.  ‎There is not an equivalent existing tax ‎
levy, other than gas and weight tax, for local roads‎.  ‎Over the next five years of the ‎
proposed CIP the total for local roads is $‎50 ‎million ‎-- ‎about $‎6‎.‎5 ‎million each year‎.  ‎
The priorities for local roads change as roads change in their need for attention‎.  ‎That ‎
has been a problem when residents have wanted a guarantee that their local road ‎
would be done in a given year and it could not be accomplished because other roads ‎
had deteriorated faster‎.  ‎With the Local Road Improvement Plan City Council has ‎
attempted to identify those roads that need to be done, those that need maintenance, ‎
and gravel roads that need paving‎.‎
 
Member Gaber added that it is not feasible or possible to identify now specific local ‎
roads that will be done in the next five years because the deterioration rate changes‎.  ‎
The city would not want to appear inflexible or unresponsive to citizens‎’ ‎needs by ‎
locking in certain local roads‎.  ‎The difference with major roads is that major roads ‎
have dedicated funding and time constraints‎.  ‎Without knowing what the condition of ‎
roads will be in five years, it is difficult to make a determination of how much money ‎
will be allocated‎.  ‎There are too many variables‎.‎
 
Another complication that Mayor Snell explained was often water and sewer projects ‎
not even in the CIP are combined with road projects in a given subdivision because it ‎
is easier and less costly to tear up a road only once, and this can cause delays for ‎
roads in other subdivisions‎.  ‎Often citizens do not realize this cost savings because it ‎
does not show up in their pockets, but it is beneficial to the city as a whole‎.  ‎Mayor ‎
Snell emphasized that the CIP Policy Team is open to other ideas on ways to present ‎
this information‎.  ‎
 
On the Local Road Projects page, Mayor Snell explained that the Legend for LR‎-‎1 ‎
Rehabilitation ‎(‎Multi‎-‎year Project‎) ‎means those are all the roads in subdivisions that ‎
have no box number associated with them‎.  ‎Rehabilitation means total reconstruction ‎
of a road and does not include overlays‎.  ‎Overlays are not shown as they are ‎
considered maintenance‎.  ‎
 
 
 
The following changes were recommended to be made to the ‎2000‎-‎2005 ‎Capital ‎
Improvement Plan‎:‎
 
 ·‎     Policy Team Recommendation page‎: ‎Remove the word ‎"‎spreadsheet‎".‎
 ·‎     The Capital Improvement Plan Support and Role Identification Pages‎: ‎Under the ‎
 Planning Commission‎’‎s role and City Council‎’‎s role modify the language ‎
 “‎...‎the Administrative Team‎’‎s recommendation‎...‎” ‎and ‎“‎...‎incorporates ‎
 the first year of the plan into the Budget Plan‎...‎” ‎in light of the Mayor‎’‎s ‎
 comments‎.‎
 ·‎     Page ‎15‎, project MR‎-04‎ should read ‎“‎a two‎-‎lane boulevard‎”‎.‎
 ·‎     Condense ‎“‎Fleet‎” ‎to one line‎.‎
 ·‎     Fit everything on one spreadsheet, if possible‎.‎
 ·‎     Identify the amount of an allocated funding source and the amount needed to be ‎
 supplemented from another source‎.‎
 ·‎     Reduce the ‎“‎Project Area‎” ‎column to a caption only at the top of each section ‎
 rather than repeating it for each project‎.‎
 ·‎     Identify what happened to Companion Projects‎.‎
 ·‎     Page ‎22‎, Local Road Projects, Legend‎: ‎Red and purple colors are difficult to ‎
 distinguish‎.  ‎
 ·‎     Page ‎23‎ under LR‎-01‎ list streets or subdivisions or neighborhoods‎.  ‎Show LR‎-03‎ ‎
 Gravel Road Upgrades in the text and spreadsheet‎.‎
 
(‎Ref‎: ‎2000‎-‎2005 ‎Capital Improvement Plan Preview dated June ‎1‎, ‎1999 ‎prepared by ‎
the City of Rochester Hills Fiscal Team, and ‎2000‎-‎2005 ‎Capital Improvement Project ‎
Book dated May ‎1999 ‎prepared for the City of Rochester Hills CIP Policy Team; ‎
1999‎-‎2004 ‎CIP Review dated ‎6‎/‎1‎/‎99‎; Enhancements to Capital Improvement ‎
Program Fiscal Year ‎2000‎.)‎
Discussed
 
ANY OTHER BUSINESS
Hamlin Road Reconstruction‎
Ms‎. ‎Goodwin explained that City Council has established some standing committees, ‎
one of which is Community Development Viability‎.  ‎The idea is that the subcommittees ‎
would take up substantive policy issues in committee and forward recommendations ‎
to City Council‎.  ‎John Gaber, Melinda Hill, Susan deCaussin, Patricia Goodwin, Tom ‎
Dohr and Bill Dinnan comprise the committee‎.  ‎One of the issues before the ‎
committee was Hamlin Road construction between Livernois and Rochester Road‎.  ‎
The Transportation Plan calls for a four‎-‎lane residential boulevard, and residents are ‎
not in favor of that‎.  ‎Council has funded the reconstruction, and the project is now ‎
pending subject to a recommendation from the Community Development Viability ‎
Committee on whether it should proceed, be modified, or abandoned‎.  ‎A question ‎
came up regarding the continued advisability or preference for a four‎-‎lane residential ‎
boulevard treatment‎.  ‎The question that has been raised is whether or not the issue ‎
should be brought back to the Planning Commission to consider whether that ‎
cross‎-‎section concept should be modified and‎/‎or whether or not four‎-‎lane boulevards ‎
are the preferred alternative for addressing traffic congestion on major roads‎.  ‎Some ‎
of the members of the committee would like the benefit of input from the Planning ‎
Commission, not to reopen the plan, but to consider two things‎: ‎Why was a four‎-‎lane ‎
residential boulevard the preferred alternative, and are there reasons why the Planning ‎
Commission might consider amending that across‎-‎the‎-‎board to three lanes or an ‎
intersection improvement only?  Jim Dietrick will be looking at various financing ‎
alternatives‎.  ‎The second issue is if, in fact, Council makes a determination that they ‎
want to reduce the right‎-‎of‎-‎way width, how then do we address the system ‎
deficiency?  ‎
 
The Chair responded that the Planning Commission spent a lot of time, meetings, ‎
thought and argument on east‎/‎west methods of crossing the city and providing for ‎
others to cross the city‎.  ‎The city paid a lot of money for a Master Transportation Plan ‎
Update consultant‎.  ‎Public Hearings were held on the Transportation Plan and there ‎
was a great deal of public input‎.  ‎The Chair would not encourage revisiting an issue ‎
that has been beaten to death just because a couple hundred residents are making a ‎
lot of noise now because it‎’‎s their ox that is being gored ‎-- ‎and at the expense of all ‎
the other residents of Rochester Hills‎.  ‎The Planning Commission does not have the ‎
time to revisit this issue‎.  ‎If Council continues a deficiency in Hamlin Road, or creates ‎
one through its determinations about budgeting or right‎-‎of‎-‎way, then the Planning ‎
Commission would have to deal with it‎.  ‎
 
Member Rosen had a hard time worrying about it for the next five or ten years ‎
because a four‎-‎lane boulevard will not happen overnight‎.  ‎If other higher priority roads ‎
are done, it will make a significant improvement in traffic congestion‎.  ‎The one lane for ‎
one mile of Hamlin Road in question does not warrant a panic at this time‎.  ‎The city ‎
has already decided to accept a certain level of congestion in order to maintain its ‎
character‎.‎
 
Member Gaber commented that City Council could pass a resolution asking the ‎
Planning Commission to reconsider this issue‎.‎
 
Member Ruggiero thought it silly to revisit the issue‎.  ‎If City Council wants to change ‎
the plan, that would be up to them‎.  ‎
 
The Chair added that the Planning Commission cannot pretend that they do not know ‎
what is driving this issue‎.  ‎There is a very small contingent of citizens that is very vocal, ‎
very organized, and very active‎.  ‎The Transportation Plan was written and approved ‎
for the entire community ‎-- ‎and as a community among other communities ‎-- ‎not just ‎
for the residents on Hamlin Road‎.‎
 
Member Rosen added that City Council can change the effect of the Master ‎
Transportation Plan by their funding actions and decisions, and it‎’‎s entirely within their ‎
prerogative to do so‎.‎
 
Ms‎. ‎Goodwin responded that one thing that makes the city‎’‎s plans very defensible in ‎
court is that there is continuity and consistency between them‎.  ‎
NEXT MEETING DATE
Chairperson Kaiser reminded Commissioners that the next Regular Meeting is ‎
scheduled for June ‎15‎, ‎1999‎.  ‎Members Gaber and Ramanauskas announced they ‎
would be absent from the June ‎15‎, ‎1999 ‎meeting‎.‎
 
ADJOURNMENT
Hearing no further business to come before the Planning Commission, Chairperson ‎
Kaiser adjourned the regular meeting at ‎10‎:‎19 ‎p‎.‎m‎. ‎Michigan time‎.‎