1000 Rochester Hills Dr
Rochester Hills, MI 
48309
(248656-4600
Home Page:  
www.rochesterhills.org
Rochester Hills
Minutes
Planning Commission
Chairperson William Boswell, Vice Chairperson Deborah Brnabic
Members:  Gerard Dettloff, Kathleen Hardenburg, Greg Hooper, Nicholas OKaltsounis, 
David AReece, CNeall Schroeder, Emmet Yukon
7:30 PM
1000 Rochester Hills Drive
Tuesday, April 15, 2008
CALL TO ORDER
Chairperson William Boswell called the Regular Planning Commission 
meeting to order at 7:30 p.min the Auditorium.
ROLL CALL
 
William Boswell, Deborah Brnabic, Gerard Dettloff, Kathleen Hardenburg, 
Greg Hooper, Nicholas Kaltsounis, David Reece, CNeall Schroeder and 
Emmet Yukon
Present
9 - 
Quorum present.
 
Also present:        Ed Anzek, Director of Planning and Development
                               Julie Jenuwine, Director of Finance
                               Roger Rousse, Director of DPS/Engineering
                               Alan Buckenmeyer, Manager of Parks
                               Jim Bradford, Fire Department Deputy Chief
                               Dan Casey, Manager of Economic Development
                               Maureen Gentry, Recording Secretary
APPROVAL OF MINUTES
2008-0153
April 1, 2008 Regular Meeting
 
A motion was made by Schroeder, seconded by Kaltsounis, that this matter be 
Approved as Presented.                                                                                                                                                                                             
The motion CARRIED by the following vote:
Aye
Boswell, Brnabic, Dettloff, Hardenburg, Hooper, Kaltsounis, Reece, 
Schroeder and Yukon
9 - 
COMMUNICATIONS
A)  Planning & Zoning News dated April 2008
B)  Memo from MGentry, dated April 152008 re:  PC Rep to ZBA
NEW BUSINESS
2008-0152
2009-2014 Capital Improvement Plan Workshop - Presentation of projects
(Reference:  Memo from Julie Jenuwine, dated April 9
2008, and draft CIP document had been placed on file and 
by reference became part of the record thereof.)
 
MsJenuwine began the workshop with a brief statement 
about the CIP process.  She summarized that the CIP was 
developed as a tool to implement the Citys Master Land 
Use Plan, and also assisted the City with its long-term 
financial planning.  The threshold for non-operating budget 
projects was $25,000.00 or more, however, Professional 
Services had to be $50,000.00 or more.  She advised that 
the Green Space Land Acquisition had been excluded from 
the process, as the committee was doing its own work.
 
MsJenuwine advised that the 2009 CIP was similar to 
those in prior years.  The Policy Committee changed 
criterion eight of the Needs Assessment Form, which rated 
projects based on saving a fixed dollar amount, because 
they felt it should be relative to the project cost.  It was now 
more of a return on investment” calculation and would 
include cost saving measures.  It was an effort to allow 
projects to get more points.  There were 11 total criteria.  
She noted that some of the projects were fairly old, and had 
not been rated in quite a few years, so they thought it would 
be a good exercise and appropriate to re-rate all the 90 or 
so projects.   The Engineering Department had asked if the 
pathways could be submitted and rated by the Pathway 
Committee rather than the Policy Team.  The Policy Team 
decided it would be appropriate, since that Committee 
focused on and dedicated time looking at and analyzing the 
pathway projects more intimately.  It was her understanding 
that the Pathway Committee was in the process of rating 
the projects and establishing a Needs Assessment Form 
that would be very similar to what the CIP Team used.  She 
hoped that by the end of April they would have the 
information accumulated so it could be given to the 
Planning Commission.  She noted that the Public Hearing 
would be May 20 to allow the Pathway Committee enough 
time.
 
MsJenuwine related that there were 19 new projects 
proposed, plus they pulled two projects from the "Under 
Review Section" (formerly the Companion Section) - the 
Dequindre Road and Water Reservoir projects.  The 21 
projects amounted to a little over twelve million dollars, City 
share.  The CIP totaled $192,500,000.00, and the City
share was around $132,000.00.  The water and sewer 
projects made up 29of the costs; local streets were 28%
major roads were 23%; internal services were 10%
pathways were 5%; drains were 3%; parks were 1%; and 
facilities were 1%.  She mentioned that none of the costs 
included any borrowing costs.  If the City bonded for any of 
the projects, such as the water and sewer projects, the 
interest costs would have to be added to the total.  Ms
Jenuwine referred to pages 86-88, and said they were a 
brief summary of the added projects, the completed projects 
and any timeline shifts.
 
MsJenuwine referred to page 87, projects removed, and 
said that some were completed and some were pulled, and 
it explained it further.  On page 88, the projects with timeline 
changes were listed, and they were generally pushed back 
because the priorities had changed or the funding was not 
available.  She noted that the Local Street PQSummary 
listed some major roads, such as Drexelgate and 
Meadowfield, because the software was not reporting as it 
should, but that they would be removed
 
The first project discussed was IS-02B, Website Update 
Project, (page 57submitted by MIS in conjunction with 
Planning and Development.   It related to a proposed 
Branding and Communications project.  MrAnzek advised 
that the Website Update was closely tied to the 
Communications plan, and that MrCasey was working with 
MIS to upgrade the web page.  They intended to unify the 
Citys image and appearance with logos, letterheads and 
similar.  
 
MrCasey stated that the City had been looking at a 
Branding and Communication Plan for a couple of years.  
The Mayor formed a Business Council about a year ago, 
and some strong recommendations from the group were 
that the City needed to do more to market itself to the 
community.  They needed to present programs and 
services available to residents and to the business 
community.  To do it correctly, they had to look at what the 
City had now.  They would take a comprehensive 
approach, and gather public and stakeholder input, as well 
as the Citys input.  The project would evaluate the current 
business cards, letterhead, cable, etc., and afterwards, they 
would decide whether the current brand was effective and 
meaningful, and if not, what could be better.  They also 
currently had competing tag lines within the City, and that 
would be evaluated to try to consolidate into one common 
theme and brand that the entire City would market.  The 
project also involved development of a major marketing 
piece the City would use for the attraction of residents and 
businesses to the community.  At the end of the project, 
there would be a document for City staff that would identify 
the types of fonts they should use in public 
communications, and when and where to use the City
logo, and things of that nature.  They would use faxes and 
news releases and business cards all concise in 
appearance throughout the organization.  The Website 
Update was a standalone project, but it would rely upon the 
results of the work related to the Communication Plan.  
Communities typically redid their websites every four or five 
years.  On the private side, most businesses redid their 
websites every two or three years.  It had been about four 
years since the Citys website was redeveloped.  The City
website could also be improved from a technology 
standpoint.  They could look at doing online permitting in 
the Building Department, for example.  The current website 
was a template-type, and they needed a fresh perspective 
to determine what type of system they wanted.  
 
Chairperson Boswell reminded that it was a workshop, and 
that the Commissioners should feel free to comment on any 
project.
 
MrDettloff stated that he fully supported the 
Communications project, and that marketing a community 
was extremely important from an attraction standpoint.  He 
asked if the City would hire an outside firm or if some things 
would be done in house.  MrCasey said that the proposal 
in the CIP assumed that a consultant would be brought in to 
manage the Branding and Communications side of the 
project.  They would do as much internally as they could, in 
terms of design and development of the marketing 
materials and templates.   MrDettloff commented that 
unfortunately, a lot of the information/technology became 
outdated quickly, and he asked if the project allowed for 
updates on an annual basis.   MrCasey said that it was a 
good question, and that the print piece would potentially be 
the only part that could be out of date quickly.  As long as 
they were cautious with how it was developed, he expected 
it to last for two or three years, but it would probably have to 
be redone after that.  
 
MrHooper agreed with MrDettloff, and said he supported 
the project.  He thought there would be many returns for the 
City for a minimal cost.  Chairperson Boswell suggested 
that there were a lot of local talents and resources in the 
City that they could tap into, and they could potentially be 
used for free.  
 
MrKaltsounis recalled that MrCasey said he wanted to 
evaluate whether what the City had was good enough.  He 
remarked that if he even had to ask that question, they 
should just change everything and save the money.   He 
thought changing the website was a step in the right 
direction and he would just do it, not ask if they should.
 
MsJenuwine next referred to IS-04(page 59), Heart 
Monitor Replacement Schedule, and said it was a new 
project, although the City had been purchasing heart 
monitors.  They decided to put it in the CIP to get it on the 
schedule as a recurring cost.  She emphasized that the CIP 
prevented things from falling through the cracks when they 
began the budget process.  
 
Deputy Chief Bradford explained that the heart monitors 
helped the paramedics monitor heart rhythms and vital 
signs, and gave a whole range of diagnostics they could 
use on the ambulances.  They were required by the State of 
Michigan to be in ambulances, and they put the project into 
the CIP to be on a replacement schedule.  MrSchroeder 
asked if they needed one for each vehicle, which was 
confirmed.  MrBradford said they had four, and they would 
replace three and add the fourth.  It was better to buy them 
at the same time.  MrSchroeder asked how one physically 
worked.  MrBradford said there were leads for EKGs to 
attach to the chest, and the information was transmitted 
over a phone from the scene to the hospital.   MrSchroeder 
said they were something the City absolutely needed, and 
he stressed that they should be the most up-to-date 
available.  
 
MsJenuwine referred to IS-05(page 59), DPS 
Maintenance Facility Floor Cleaner.  MrRousse advised 
that the proposal was for purchase of a sweeper for the 
interior of the new DPS garage.  The existing street 
sweeper created too much dust and affected the lighting.  
The device was more than a sweeper it was also a 
cleaner.  When the building was cleaned after construction, 
they rented one.  The cleaning feature sprayed detergent, 
and they felt it would greatly prolong the life of the floor.  Ms
Hardenburg asked how often they would use it, and Mr
Rousse said it would be done weekly, maybe more during 
the winter.  MsHardenburg asked the cost to rent one, and 
was told $500 per day.  She asked how long it took to use it, 
and MrRousse answered about four hours.   MrSchroeder 
asked if it had a vacuum.  MrRousse advised that it was a 
combination of detergent sprayer for the grease and 
something to capture the sand and gravel.  MrSchroeder 
said they should get it as soon as possible for the new floor.  
MsHardenburg commented that the information would 
have been nice to have earlier when they rated the projects.  
She was not aware they were using the street sweeper.  Mr
Hooper asked if the funding for the internal service program 
was from the Water and Sewer funds.  MsJenuwine 
agreed, and said they considered that the building was 
owned by the Water and Sewer Fund.  MrDettloff asked the 
average longevity for a floor cleaner.  MrRousse said that 
if it were properly maintained, it should last 12-15 years.  
MrSchroeder clarified that it was diesel powered.  Mr
Yukon asked what type of maintenance was required.  Mr
Rousse said it had a higher maintenance frequency, but the 
City was well equipped to provide that.  
 
MsJenuwine said that IS-07B, City-wide Records 
Management Implementation, had already begun.  There 
had been an analysis over the last couple of years, which 
was the first phase.  Originally, the project was in the CIP for 
almost two million dollars, because they did not know what 
the results of the analysis would be.  It was her 
understanding the consultant determined that things were 
not too bad, and the City was not in need of much software 
to manage the various records.  The implementation 
included selection of the main document management 
platform and installation of a vital statistics management 
system module basically, the births and deaths records at 
Clerkto replace the existing, obsolete system from 1997.  
The second phase was about $200,000.00 (the first was 
$100,000.00), and included the large-scale format plan 
imaging system.  That would mostly help Building, 
Engineering and Planning to record large documents 
electronically.  Fortunately, the projects estimation 
decreased significantly from its original submission.  Mr
Schroeder asked if it included copying all the documents, 
and was told no.  MrHooper asked if the funding would 
come from the General Fund, and MsJenuwine said that it 
ultimately would.  
 
MsJenuwine referred to LS-12 and MR-12 (pages 30 and 
24), Local and Major Street Traffic Calming Programs.   Mr
Rousse said that the projects were intended to jump-start 
the seed funding for a proposed pilot program.  The City 
received complaints from residents and a traffic study was 
done.  That information was taken to the Advisory, Traffic 
and Safety Board and a recommendation was made 
regarding speed humps for calming traffic.  The 
Homeowners Associations generally did not have the 
money to install them, and consequently, the goal of 
achieving traffic speed reduction was not reached.  The 
local road would have a 50-50 match with the Homeowner
Association.  The major road would be funded 100by the 
City.  A number of subdivisions had expressed interest, and 
the City felt it could accomplish a great deal with the 
devices.  They were already in the Arcadia Park and 
Powder Horn subs, and they worked quite well.  They were 
different from speed bumps.  The residents would have to 
approve them, and if they ever wanted them removed, the 
Homeowners Association would have to pay for it.  
 
MrSchroeder asked if they had problems with the 
snowplows.  MrRousse said they had to alert the drivers to 
let up on the plow pressure.  MrSchroeder asked if there 
was signage to warn them, and MrRousse said there were 
street markings and signs.  MrSchroeder wondered if there 
were problems with kids playing on them.  MrRousse said 
that the design was rather unique, and if someone went 
over the local speed, it was a real jarring jolt.  MrSchroeder 
said that in his experience, residents had never wanted to 
go along with it.   
 
MsHardenburg asked who was responsible for repairing 
them.  MrRousse said that the City would be responsible 
for any repair or maintenance and painting.  MrHooper 
said he drove over one in Arcadia, and he said it was more 
like a speed table.”  It was about 18 feet and flat on top.  He 
went over the speed limit about 10 miles per hour to test it, 
but he did not feel it did much.  MrRousse said they got a 
lot of requests for stop signs, but that they did not really 
slow people down.  They found that an unwarranted stop 
sign actually increased the speed.   MrSchroeder said that 
residents usually ignored unwarranted stop signs.  Mr
Hooper asked if the fire trucks had problems with the speed 
tables, and according to MrRousse, they apparently did 
not.  MsHardenburg said they put empty tricycles in 
driveways in her neighborhood to slow vehicles.  People 
started looking for children nearby and slowed down.  Mr
Kaltsounis mentioned that in Novi, they took out speed 
bumps after a year because of the fire trucks.  MrDettloff 
asked if the noise issue was a non-issue where the devices 
were currently at, and MrRousse advised that they had not 
received any complaints.  
 
MrYukon asked how the devices were installed.  Mr
Rousse said that the asphalt was ground down and they 
were built on top of that.  It could not be knocked off, but 
was an integral part of the road.  It was best if it was 
installed initially with the asphalt, but there were other 
techniques.  MrYukon asked what they used for concrete 
streets.  MrRousse said it was a challenge, and that the 
CIP projects were asphalt.  MrYukon asked if they had 
traffic-related concerns for certain concrete streets, and Mr
Rousse said that they did, but the largest amount of 
complaints came from subdivision homeowners.  
 
MsJenuwine referred to proposed lighting for Crooks, 
Hamlin, Livernois, Walton and Adams.  MrRousse said 
that the CDV had actually approved a street lighting policy.  
The most attention for Council was during the Crooks Road 
project.  At that time, the proposal was for three different 
types of street lighting.  One was similar to the lighting in 
Troy, another had certain lighting for the residential and 
another for businesses.  Council decided they wanted to 
think about it and the policy never got formalized.  They 
added underground piping for the electrical and irrigation 
when they did Crooks.  He noted that funding might 
become available through the Metro Act, which prompted 
the proposals throughout the City.  MsHardenburg asked if 
the funding helped pay for irrigation also.  She asked if 
there was enough funding to do both, questioning whether 
the City would want a lit area or a green area.    
 
MrRousse stated that the proposal staggered the projects.  
It would not use all the funding at once.  MsHardenburg 
said it would eventually all be in and have to be paid.  She 
said they had to look down the road and at maintenance, 
which was ongoing.  She thought that having the 
underground in as they redid the roads made sense.  She 
commented that the Planning Commission talked with 
developers about reducing light pollution, but the Advisory 
and Traffic Board talked about lighting things up.  It was a 
contradiction, and she felt they all needed to be on the 
same page.  MrSchroeder agreed it was a problem.
 
MrHooper agreed with MsHardenburg.  He thought they 
should first do the irrigation, but he was not sure about the 
lighting.  MsHardenburg said that if the piping was put in 
with the road and in the future something was available, 
that was different, but she did not think they should tear up 
the roads.   MrHooper asked if there were dark 
intersections that might create a need for lighting.  Mr
Rousse said that each proposal would be preceded by a 
lighting study for the casting of the lights.  He noted the 
school on Crooks, and said one proposal was to put lights 
just at the intersection and on each side of the school.  Mr
Hooper reminded that energy conservation was high on the 
list of goals and objectives, and secondly, that there was a 
funding issue.  He thought green grass would be more 
aesthetically pleasing.  If they put lights on Crooks, he 
could envision complaints from the people living on 
Crooks.  Hamlin Road, where no one lived, was a different 
story.  MsHardenburg asked why it would be lit.  She 
wondered if lighting should even be kept in the CIP 
because if it were, eventually Council would have to 
entertain it.  
 
MrKaltsounis said he was happy to see it planned for 
Crooks Road.  He was often asked why the City of 
Rochester Hills was so cheap about lighting.  When people 
came to Rochester Hills, their first impression was of 
darkness.   He agreed with energy conservation, and would 
suggest single pole lighting rather than double.  Ms
Hardenburg said there were some people who did not like 
glaring lights.  MrReece maintained that they had to 
balance the peoples’ needs, but he cautioned about being 
contradictory from an energy conservation standpoint.  
They would literally be throwing a lot of money down the 
drain watering all the nice boulevards.  He said there were 
other options besides putting down seed and watering it
 
MrSchroeder added that it was a battle the residents were 
in opposition, and it was a safety feature that should be 
given to the drivers.  He suggested that they could reduce 
the wattage, put in a flat rather than a curved lense, and put 
shields in the back, but even with no spillover to the 
residential, the people could still see it and argue about it.  
He stated that it was a struggle every time, and in the past, 
the City of Rochester Hills had always listened to the 
residents.  
 
MrKaltsounis asked if they had ever looked into drilling a 
well in those areas, rather than paying for water from the 
City of Detroit.  MrSchroeder advised that there would be a 
lot of maintenance, and it was expensive and there was 
really not a payback.  The water table dropped with each 
development.   MrRousse said they evaluated it, but it 
would have required a couple of wells and they would have 
to be very deep and would be costly.  He pointed out that 
through proper maintenance, the cost of water could be 
reduced.  A new lawn required a lot of water, but once it 
matured, it only used one inch of water per week, 
depending on the conditions.  
 
MsBrnabic said that she would personally like to see both.  
She was not totally against lights, because they were 
necessary for safety.  There were certain areas of the 
community that were very dark.  There was a lot of bad 
weather this year, which hampered visibility, and there were 
times it was very difficult to see the roads.  She would like 
to see a plan of where they might go and determine if they 
could have lighting and irrigation.  MrRousse mentioned 
LED lights, and said that there could be something on the 
horizon that could greatly reduce the energy costs.   He 
also pointed out that there were a lot of pathways used, and 
that in certain locations it seemed appropriate to add 
lighting.   
 
MrSchroeder referred to irrigation, and noted that 
Somerset Apartments in Troy had a wet detention pond that 
they pumped water from for irrigation.  If the City had one, it 
would work well, although he could not think of one along 
Crooks.  MrAnzek asked if they discussed landscaping for 
the boulevards.  MrRousse said they planned to have 
finished lawn in those areas.  He said that Crooks was a 
County road, but they left that portion of the maintenance up 
to the City.  The County did not provide the level of finished 
cut mowing the City would like so they assumed the 
maintenance
 
MrAnzek said he was hearing differences of opinion from 
the Commissioners as to whether it should be lights or 
landscaping.  He felt that discussion needed to be held with 
Council to firm up a policy before the Commission was 
asked to support it in the CIP.  He asked if it would be 
acceptable to push each of the items back another year 
until the discussion.  MrRousse agreed it was a good 
suggestion, and said it would give them more time to 
evaluate.
 
MrSchroeder said they really needed to look at Livernois, 
and MsHardenburg agreed it was a mess because all the 
trees had died.  MsHardenburg said that MrReece 
mentioned there were other options, such as stonework or 
low ground cover that did not need mowing.  MrHooper 
said that Council looked at that last year, and the plants had 
to be salt-resistant, which ruled most everything out.  Mr
Rousse noted that the Livernois boulevard was narrow and 
it got hot in the summer and the conditions for growing 
grass were harsh.  When the Livernois boulevard was 
initially installed, there was approximately $100,000.00 
worth of plantings installed.  In five years, about 80had 
died.  They did not want that to happen again, and the first 
solution was to use irrigation.  
 
MrCasey noted that Hamlin was proposed for construction 
next year, and he asked if it would be appropriate to install 
irrigation at that time, or at least the infrastructure for lighting 
and irrigation.  MrRousse advised that they were doing the 
underground infrastructure, and they found it was better to 
put the irrigation in after the project was completed.  Mr
Schroeder said he would agree 100%.  They had problems 
in Troy with State contracts, and the State was very loose 
with requirements for landscape and irrigation contractors.  
They would buy the cheapest materials, and Big Beaver 
was a disaster.  Somerset Mall took out the landscaping 
and replaced it.  They put the conduits in to service the 
irrigation after the contract was done.  They waited until the 
maintenance period for the contractor was over, and it was 
a much better job.
 
MsBrnabic asked why it took five years to evaluate 
Livernois.  The average driver had noticed it sooner, and 
she had numerous comments regarding it over the years.  
MrRousse said it was initially proposed with irrigation, and 
when the bids came in, they decided to take it out and try 
another type of ground cover, with wood chips.  The idea 
was that when the trees grew, they would provide shade 
and protect the grass.  Unfortunately, the ground was heavy 
clay and the trees did not grow and the weeds took over, 
even though they treated the weeds.  
 
MrYukon asked if there was a specific criterion that had to 
be met when street lighting was installed, such as pole 
placement for each area.  He asked if they placed the poles 
according to where the residents were so there would not 
be a problem and how that worked.  MrRousse said they 
first did a casting study, which gave an idea where the 
lights would cast.  One proposal was for a cobra light 
mounted in the middle of the boulevard with two heads to 
light the street.  Another alternative was for a single pole at 
the intersections.  In many cases, the business community 
would provide enough lighting so exterior lighting could be 
minimized.  MrYukon clarified that the study would take 
residential areas into consideration.  MrAnzek asked if the 
Michigan lefts counted as intersections, noting that those 
areas also needed lighting.  MrRousse said that the 
primary concern was for pedestrians coming out of the side 
streets because on local roads, there were no pathways.  
MrSchroeder said that with cobra lighting, you could direct 
the lighting toward the roads, away from the subdivisions.  
MsHardenburg questioned whether they would light the 
pathways or the boulevard, and MrSchroeder said it would 
primarily be for the median.  MrRousse reiterated that a 
lighting policy was listed on the Councils goals and 
objectives, and he felt that a years delay would be 
appropriate.  MrSchroeder said that the materials should 
be consistent throughout the City.  MsHardenburg added 
that they did not necessarily have to be consistent with 
Troy, because it was a different community.
 
Chairperson Boswell moved to the next item, MR-04A, 
Walton Rehabilitation (Adams Livernois).  MrRousse said 
it would be a joint project with the Road Commission, 
because Walton was a County road.  There would also be 
federal funding, and the Citys contribution would be 10%.  
The road seemed to have structural stability, but there were 
a number of joint failures.  It would not need to be fully 
rebuilt, but it needed resurfacing.  The scheduling was very 
specific for 2011.  
 
The next project was the relocation of Dequindre (Avon 23 
Mile, MR-13A).  MrAnzek said that through the Master 
Thoroughfare analysis, doing something with Dequindre 
that improved movement through the Avon and 23 Mile and 
Dequindre intersection would solve a lot of problems for 
residents of Shelby, Rochester and Rochester Hills.  
Macomb was treating 26 Mile like the next Hall Road, and it 
would create a better flow on Dequindre, which would take 
the burden off Washington and Tienken.  It would lessen 
the need to widen Tienken.  It would be a long-term project, 
and they were meeting with Shelby Township the next day.  
It was a high ranking project in the Master Thoroughfare 
Plan process.  MsHardenburg asked what it would do to 
Yates Cider Mill.
 
MrAnzek said they would be very careful to miss it.  Ms
Hardenburg asked if the road would be moved, and Mr
Anzek said it would swing into Macomb a little to miss the 
historic building.  The project would take a long time, but 
with three cities involved, they felt there would be a better 
chance for federal funding, and they wanted to get started.  
MrSchroeder thought it would be hard to get federal 
funding because of the cost.  It would take ten years or 
more to get the project through.  MsHardenburg asked why 
it was dropped a few years ago, and MrAnzek said the 
person who put it on there believed that it had a limited 
chance of success.  The three cities had identified it as a 
need, however, and they were trying to get a coordinated 
effort going, so they put it back in the CIP.  MrSchroeder 
said that Macomb County had a lot more success than 
Oakland County getting funding, and that they were good to 
work with.  
 
MrDettloff asked when the project was first put in the plan.  
Chairperson Boswell said that it was identified in 1989.  Mr
Reece asked if the cost included acquisition of property, 
and was advised that it did not.   He asked if the costs 
included any type of escalation, noting the project was not 
scheduled until 2014.  MrSchroeder said they were 
projected at todays prices.  MrReece said he agreed, in 
principal, with the need to align Dequindre, but he felt there 
were missing costs, and that the reality of it happening with 
the States funding issues were slim, and he said he would 
like to see the money used elsewhere on roads in the City.  
MrAnzek said it was not being prioritized highly at the 
expense of other projects, but it was one project that would 
do the most to relieve by-pass traffic that did not start and 
end in Rochester Hills, but went through it.  He agreed the 
right-of-way costs were not included, but noted the fact that 
there were wetlands that would make it more of an 
environmental issue.  They would have to build two 
bridges.  MrSchroeder said they had to be careful about 
improving intersections.  There was a grading system for 
funding accidents, volume of traffic and when they filled 
out forms points were issued.  If they improved the 
intersections and also wanted to improve Dequindre, they 
might get zero points and have to pay 100of the costs.  
They had to look at the big picture and not get too carried 
away with intersection improvements.  
 
MrBuckenmeyer explained PK-11, the Clinton River 
Access project.  He said it was for a parking lot to the river
edge and for a handicap accessible launch.  They might 
couple it with the Restoration project for the Clinton River.  It 
would serve as a launch for anyone who wanted to go from 
the Rochester Hills site downriver.  MrYukon asked what 
the operating costs would be.  MrBuckenmeyer said that 
over the life span there would be simple maintenance 
because of the hard packed surface and the manufactured 
launch.  They might have to pull it out in the winter, so there 
would be some labor.  MrKaltsounis said there was 
already a parking area there, and he asked if they wanted to 
expand it by 15 spaces.  MrBuckenmeyer said it was for 
the other side of the river (west side of Livernois), where 
there were no parking spots.  There used to be a house 
sitting there.  MsHardenburg asked if it was for the 
take-out” for canoes at that spot.  MrBuckenmeyer said 
that the launch would be handicap accessible, but there 
was nothing downriver before the dam at Yates to take 
canoes out.  They were looking upstream in Auburn Hills to 
do something similar because there was no place to take 
them out with an accessible launch.  MsHardenburg said 
she wished the information had been given at the policy 
meeting.  They were told there would be a place to put 
canoes in, and that they would be taken out at Yates.  They 
would not be put in at Yates.  MrAnzek clarified that when 
the project was submitted, they thought it would be ideal to 
put it in at Livernois and get canoes out at Yates.  Looking 
further into that, they found they would have to make it ADA 
compliant, which Yates was not, and they might work 
something out with Auburn Hills.  Livernois would be an 
egress point for ADA.  MsHardenburg said there would still 
have to be ADA compliance for people to get out.  Mr
Anzek agreed that if they did the project, it would.  Ms
Hardenburg asked if this went along with the part of the 
Trail that needed to be repaired.  MrRousse noted the 
project for Trail restoration (SW-08B, Clinton River Natural 
Channel Restoration).  
 
MrAnzek brought up the M-59 Corridor Study (PS-14), and 
said that the Planning Department came up with three 
studies, two of which were added projects the M-59 
Corridor and the Landfill Area Study and they revamped 
the Old Towne Study.  That project had been in the CIP, but 
it had been stalled in trying to deal with the merchants 
along the Auburn Road corridor.   The new Economic 
Development Assistant, Clarinda Harrison, had suggested 
that they not just look at the corridor, but they should look at 
how it would impact the Brooklands neighborhood behind 
the corridor.  They wanted to do a better study for the entire 
area, which would be done mostly in-house.   He continued 
that in conjunction with the Master Plan that was adopted in 
February of 2007, there were discussions about the 
Regional Employment Center, and how they would promote 
and support that area.  MrAnzek said there was also an 
overlay landfill area in the Master Plan, and policies to be 
considered.  They needed to find out more about the landfill 
areas and the environmental impacts, and would do a study 
and more research using a consultant.
This matter was Discussed
MrCasey discussed the M-59 Corridor Study project next, 
noting that during the Master Plan review, they 
contemplated doing a corridor study for the Regional 
Employment Center down the road.  The purpose of the 
study was to look at the feasibility of multi-story office along 
M-59.  There were already a couple of consent judgments 
in place that provided for six and eight stories (the Grand 
Sakwa and Madison Park properties).  There were other 
areas within the REC on M-59 where it might make sense 
for redevelopment purposes in the future.  The 
considerations for the study would be to look at existing 
land uses, transition of land uses, a market study of office 
development, and existing and future development.  They 
would look at the connectivity of road systems and 
pathways, infrastructure capacity, potential redevelopment 
areas, and they would continue to evaluate roads like 
Leach and Devondale.  They would look at design 
standards as well.  There were existing light industrial and 
high tech parks within the REC, but as redevelopment 
occurred, they needed to determine how to connect the 
parks with those areas, and how they would transition away 
from M-59 in terms of height and appearance.  Those were 
all aspects of the study, and the study area would be from 
Auburn north to Hamlin and from Adams east to Crooks.  
They would require the services of a consultant to do the 
study, which would be funded by the LDFA.
 
MrYukon asked how long the study would take, and Mr
Casey advised that it would be five to six months.  Mr
Yukon asked what the next step(swould be after the study 
was completed.  MrCasey said they would use the 
document to market the area for redevelopment, so they 
would need to develop marketing materials.  He explained 
that the LDFA had a master infrastructure plan that was 
developed in 1996, which was now out of date.  The 
corridor study had to occur before doing another 
infrastructure plan because the connectivity aspect could 
be affected.  They were beginning to do the preliminary 
engineering for the extension of Austin Ave., which was a 
CIP and LDFA project.  They would pave Austin to 
Devondale, but looking long term at the potential 
redevelopment of the mobile home park, they would need 
to extend Austin further west.  
 
MrAnzek said that McKenna was working on the Regional 
Employment Center overlay district for the Zoning 
Ordinance update.  If the Corridor Study showed something 
different, that might change the REC setbacks, height or 
other incentives.  He stated that there was more to the M-59 
Corridor Study than looking at height and placement.  He 
asked if there were questions about the Landfill Area Study.  
MrSchroeder asked if it would include all the landfills, and 
MrAnzek said it would be for the entire City.  MrHooper 
said he would like to see the revolving fund from brownfield 
activities used rather than the General Fund.  MrAnzek 
agreed that if they were collecting money from the 
Hamlin-Adams redevelopment, for example, it would be 
used to fund the studies.  MrAnzek said they had identified 
13 landfills in Rochester Hills.  MrHooper said he 
supported the studies, but they would all be in competition 
for General Fund dollars.  MrAnzek said he felt that the 
numbers were a little generous, and that a lot would be 
done in house.  They could begin crafting the skeleton of 
the studies and then decide about focusing on the 
environmental work.  
 
MrRousse referred to the SCADA System Update, SS-01B, 
and said it was a project that became apparent when they 
constructed the new DPS garage.  They went to relocate the 
equipment and the vendor would not touch it.  The system 
was about six years old, but the vendor said it needed a 
new head system.  There was a data collection component, 
which sent signals.  SCADA was an acronym for System 
Control and Data Acquisition.  It was used to monitor the 
activities at the pump stations, lift stations and at the PRV 
pits.  It had the capability to make adjustments from a 
central processing unit.  It would also alert Staff to any 
failures at the pump stations.  No one wanted to move it, 
and one vendor said they had to replace the whole thing.  
The system was still located in the old DPS garage and 
they wanted to move it.  There had been money in the 
budget for a couple of years to upgrade the system, but they 
needed to put in two new servers and update the software.  
The original system had a number of patches but they 
could not find a vendor to service it now.  
 
MrSchroeder said it would be from an Enterprise Fund, 
and it was something that was needed.  If there was one 
problem with a sewer backup, it would be worth it to have.  
He said he would not fool around with an old system; he 
would get a whole new system.  If they tried to mix the old 
and new, they would have nothing but problems.  Ms
Hardenburg asked if there was money in the budget for it.  
MrRousse said they proposed to submit it as a budget 
amendment in the second quarter of 2008.  
 
MrKaltsounis asked the age of the current system, and 
was told it was installed in 2000.  There were four vendors 
that worked on it and it had a lot of patches.  They did not 
have any backup now, and the new system would be a dual 
system, with a primary and a backup should the server fail.  
MrKaltsounis remarked that they would see it again in 
three years.  MrRousse said that the system would be 
almost identical to what was used in Detroit.  
 
MrDettloff asked if the update would alleviate the problem 
of working with a lot of vendors.  MrRousse agreed, and 
said that the proposal was for a design, build and 
maintenance for three years with the same vendor.  They 
had to bid it out every three to five years.  MsHardenburg 
asked if they had any problems with the current system and 
if they needed a backup system.  MrRousse said they had 
been very fortunate that it had not crashed.  MsHardenburg 
questioned the need for a new system since they had not 
had a problem in eight years.  MrRousse advised that they 
had lost some of the reports because of the patches.  The 
reports showed when a call came, who responded, the time 
it took, and those types of things.  They needed reports 
about the pump stations also.  MsHardenburg asked if he 
really saw a need for a backup system, reiterating that there 
had not been one for eight years, and MrRousse stressed 
that they did.  MrSchroeder remarked that they had been 
living a charmed life.”  
 
MrRousse referred to the Rewold Drain (Phase Dproject, 
SW-05D, which was the fourth stage of the project.  It started 
just east of Rochester Road on Avon and went in a 
southeasterly direction to service that area.  It was a 
continuation of other projects that occurred upstream to 
address drainage problems along Avon.  MrSchroeder 
asked if it was a County project on the books.   MrRousse 
said the other projects were, and they were looking at it for 
this stage.  He noted that the Citys administrative costs 
were higher with a County program.  MrSchroeder 
recommended doing it without the County to keep the costs 
down.  MrRousse claimed that they ended up fielding the 
complaints and design issues anyway.  
 
MrHooper asked if the drain projects were all funded by 
the Major Road Fund.  MrSchroeder said it was only for the 
portion of the drainage that went into the drain, which was a 
very small percentage.  MrHooper asked if was split 
between the General Fund and Major Roads.  Ms
Jenuwine explained that that the drain projects historically 
seen in the CIP had been expended under the Drain Fund, 
which was really money from the General Fund.  It was 
currently in existence to support the construction projects in 
the CIP, but they had not been putting money there for two 
or three years.  She advised that ultimately, it was General 
Fund money.  MrHooper asked if SW-03 (Karas Drain 
Extensionshould be planned for 2009 construction.  Mr
Anzek said that construction was planned for 2009 and 
right-of-way was taking place currently.  MrHooper said 
that it showed construction planned for 2008, but he stated 
that it should be for 2009.  MsJenuwine said she would 
verify the dollars in the budget, but she felt it was a 
significant part of the estimated Citys cost, and that the 
construction should start in 2008.  MrHooper said that the 
only portion the City would do this year was the 
right-of-way, and he asked if there would be a budget 
amendment.  MsJenuwine said that if they were not on 
track, it would probably be deferred.  MrHooper believed 
that there would not be a shovel in the ground this year
 
MrRousse moved on to the Clinton River Natural Channel 
Restoration, and said they hoped to implement the project 
following a 319 grant for the planning.  He described that 
during periods of high flow, the banks of the River eroded 
and the River became wider and shallower.  The 
Restoration Plan would keep the channel deep and the 
water cooler for fish.  There would be two phases to the 
project; the first would be the grant for the channel planning 
and designing the repairs.  He showed some photos of the 
erosion to the River over the last 45 years and the portion of 
the Trail that was threatened.  The River was about 15 feet 
from the edge of the Trail.  Phase two would be the 
construction for the Channel Restoration.  They would 
survey the remaining mile of the River and determine how 
to maintain the cooler depth for better fish habitat.
 
MrHooper asked if the project could be paid from the 
Pathway Millage.  MrRousse said that a portion of the 
proposal would come out of that fund.  MrHooper asked if 
up to 100of what threatened the Trailway could come 
from the Pathway Millage, to which MrRousse agreed.
 
MrKaltsounis referred to an area where the Clinton River 
crossed Crooks Road, and said there was water seeping 
from the River up through the pavement all winter long.  He 
asked if there was a potential for failure there.  MrRousse 
said he would investigate it, because it was the first he had 
heard of it.  He thought that the elevation of the River was 
such that it was unlikely to be River water.  There possibly 
was a water main, or one of the many springs that seemed 
to pop up.  MrKaltsounis said it had been that way for over 
a year.  MrAnzek agreed it was always wet in front of 
Heritage Oaks.  MrKaltsounis said he brought it up 
because the shoreline might be eroding there and there 
was nothing about a fix for it in the CIP.  MrSchroeder 
added that there were a lot of wetlands in that area.
 
MrAnzek referred to the last new project, the Water Storage 
Facility, and asked MrRousse to explain.  MrRousse said 
it had a long history, which started in 1998.  There was an 
evaluation of the water distribution system relative to fire 
flow rates.  At that time, it identified four sections of the City 
that did not have the needed flow rate in the water mains 
during the peak demands of summer months.  The 
preferred method to address that was water storage.  They 
actually had some water shortages in the northwest corner 
of the City, and the residents complained they had low or 
no water pressure.  They found that there was a deficiency 
in the line size of the water main.  They added a pump 
station, which helped somewhat, but because there were 
about 2,500 more residents, the problem was not going 
away it was getting worse.  They hired a consultant to look 
at everything, and they supported the Water Storage 
Facility.  They looked at peak rates the City paid and came 
back with a proposal for savings for purchasing water.  
There would be a four to seven-year return on investment 
for the facility.  It was coupled with the DPS garage and the 
bonding was approved by City Council for both.  They built 
the DPS garage, but put the water storage facility on hold.  It 
had been brought forward again to try and address the 
issue of water supply and for the low flow areas identified.  
 
MrSchroeder asked if the Detroit Water Board agreed with 
it.  MrRousse said they placed some restrictions on the 
City.  MrSchroeder said they looked at it in the 1970s, 
when he worked for the City.  They met with Detroit, and 
they would not allow Rochester Hills to have any storage.  
MrRousse said that at that time, Detroit wanted the 
storage, and they built reservoirs in the CityThat did not 
address the internal size of the water mains.  MrSchroeder 
asked where the Storage Facility would be.  MrRousse 
said they had identified possible locations:  One reservoir 
just north of Avon on John R., and one on Tienken just west 
of Adams High School.  MrSchroeder said that would be 
closer to the problem.  MrSchroeder asked if the tank 
would be buried, and MrRousse said that the DEQ was 
steering them away from that.  MrSchroeder asked if there 
would be a tower, and he was informed that it just had to be 
above ground.  MrSchroeder asked if it could be covered 
with trees, and MrRousse said it would be about 45 feet 
high and 80 feet wide, and it could be decorated with 
concrete pilasters or something similar.  He had seen one 
with a tennis court on the top, and he had seen pump 
stations that looked like homes.  MrKaltsounis recalled 
that there was one in Royal Oak painted a dark green gloss, 
which he thought looked great.  MrSchroeder noted that 
Beverly Hills had a nice one that looked like an old 
fashioned barn.  
 
MsBrnabic mentioned that she felt it would be very helpful 
to have a column with page numbers for each new project 
added (page 86).  She questioned why the CIP document 
was organized the way it was, and thought it would be 
helpful to alphabetize it.  She was not sure if there was a 
purpose to the way it was organized, and MsJenuwine 
said that they could certainly change the order.   Ms
Brnabic thanked Staff for the CIP presentation and 
explanation.  
 
MrAnzek reminded that any subsequent questions should 
be directed to him or MsJenuwine.  It was important to 
adopt the CIP in May because it was critical for the budget 
preparation.  MrHooper referred to page 25, Adams Road 
Traffic Signal, and asked if the Advisory, Traffic and Safety 
Board had talked about it.  MrAnzek said they did not get 
into that detail.  MrHooper asked about installing a 
roundabout at Adams and Butler instead.  MrRousse said 
that all the environmental assessments would consider 
different configurations, and before they got to that phase, 
they would look at different designs and evaluate.  He 
thought that a roundabout was a great solution to traffic 
patterns.   Drivers got used to them, and they moved traffic 
well.  He had heard people voice concerns about the 
learning process.   MsHardenburg said she hoped they 
were looking at a new traffic configuration at Drexelgate and 
Livernois, because when the roundabout was installed at 
Hamlin and Livernois, people would use Drexelgate to get 
to their homes, and there was no left turn signal there now.
 
MsBrnabic noted a correction to page 19, which said that 
the update to the Master Thoroughfare would be completed 
by the end of 2007, rather than 2008.
This matter was Discussed
ANY OTHER BUSINESS
2008-0190
Request to Confirm the Mayor's reappointment of Deborah Brnabic as Planning 
Commission representative to the Zoning Board of Appeals for a one-year term to expire 
March 312009.
MrSchroeder moved the following motion:
 
Motion by Schroeder, seconded by Hardenburg, the 
Planning Commission hereby recommends to City Council 
that Deborah Brnabic be its representative on the Zoning 
Board of Appeals for a one year term to expire March 31
2009.
 
A motion was made by Schroeder, seconded by Hardenburg, that this matter be 
Recommended for Approval to the City Council Regular Meeting.                                                                                                                                                                                             
The motion CARRIED by the following vote:
Aye
Boswell, Brnabic, Dettloff, Hardenburg, Hooper, Kaltsounis, Reece, 
Schroeder and Yukon
9 - 
NEXT MEETING DATE
The Chair reminded the Commissioners that the next Regular 
meeting was scheduled for May 62008.
ADJOURNMENT
Hearing no further business to come before the Commission, 
and upon motion by Kaltsounis, the Chair adjourned the 
Regular Planning Commission meeting at 9:50 p.m., Michigan 
time.
 
 
 
_____________________________
William FBoswell, Chairperson
Rochester Hills Planning Commission
 
 
 
_____________________________
Maureen Gentry, Recording Secretary