File #: 2023-0504    Version: 1
Type: Project Status: Passed
File created: 10/25/2023 In control: Planning Commission
On agenda: Final action: 11/14/2023
Title: Request for Tree Removal Permit approval - File No. PTP2023-0013 - to remove forty-nine (49) regulated trees and three (3) specimen trees and to provide thirteen (13) trees onsite with the remaining forty-eight (48) trees to be paid into the City's Tree Fund for Hamlin Road Storage Facility at 1575 E. Hamlin Rd., located on the north side of Hamlin between John R and Dequindre Rd., zoned I Industrial, Parcel No. 15-24-401-006, Steve Osborne, CDK Development, LLC, Applicant
Attachments: 1. Staff Report 091423.pdf, 2. Fenn & Associates, Inc. letter 063023.pdf, 3. Reviewed plans 100523.pdf, 4. Development application.pdf, 5. Notice of Public Hearing.pdf

title

Request for Tree Removal Permit approval - File No. PTP2023-0013 - to remove forty-nine (49) regulated trees and three (3) specimen trees and to provide thirteen (13) trees onsite with the remaining forty-eight (48) trees to be paid into the City's Tree Fund for Hamlin Road Storage Facility at 1575 E. Hamlin Rd., located on the north side of Hamlin between John R and Dequindre Rd., zoned I Industrial, Parcel No. 15-24-401-006, Steve Osborne, CDK Development, LLC, Applicant

 

Body

Resolved, in the matter of File No. PSP2023-0014 (Hamlin Road Storage) the Planning Commission grants a Tree Removal Permit (PTP2023-0013), based on plans received by the Planning Department on September 20, 2023, with the following findings and subject to the following conditions:

 

Findings

 

1. The proposed removal and replacement of regulated trees is in conformance with the City’s Tree Conservation Ordinance.

 

2. The applicant is proposing to remove forty-nine (49) regulated trees and three (3) specimen trees with 61 replacement trees required. The applicant is proposing to provide thirteen (13) trees onsite with the remaining forty-eight (48) trees to be paid into the City’s Tree Fund.

 

Conditions

 

1. Tree protective fencing, as reviewed and approved by the City staff, shall be installed prior to temporary grade being issued by Engineering.

 

2. Provide payment, equal to the current required fee for replacement trees and as approved by Staff, along with any additional fees associated with such, into the City’s Tree Fund for the remaining 48 trees identified on the site plan.