File #: 2008-0411    Version:
Type: Project Status: Passed
File created: 8/5/2008 In control: City Council Regular Meeting
On agenda: 8/19/2008 Final action: 10/6/2008
Title: Request for Wetland Use Permit - Rayconnect, Inc. Industrial Building, to impact approximately .28 acre to develop a 51,800 square-foot industrial building with a 9,330 square-foot office on 9.8 vacant acres (two parcels) located at Austin and Devondale, zoned I-1, Light Industrial, Kirco Development, applicant
Attachments: 1. Agenda Summary.pdf, 2. Site Plans.pdf, 3. Map.pdf, 4. Staff Report.pdf, 5. Letter ASTI 091908.pdf, 6. Minutes PC 081908.pdf, 7. Resolution.pdf
Title
Request for Wetland Use Permit - Rayconnect, Inc. Industrial Building, to impact approximately .28 acre to develop a 51,800 square-foot industrial building with a 9,330 square-foot office on 9.8 vacant acres (two parcels) located at Austin and Devondale, zoned I-1, Light Industrial, Kirco Development, applicant
 
Body
Resolved, that the Rochester Hills City Council hereby approves a Wetland Use Permit to impact approximately .28 acre for industrial use construction (parking, loading, fire lane and detention basin) for the Rayconnect, Inc. Industrial Building project, a 61,000 square-foot industrial building and office located on 9.8 vacant acres at Austin and Devondale, zoned I-1, Light Industrial, Parcel Nos. 15-29-452-027 and -028, with the following findings and conditions:
 
Findings:
 
1.  Of the approximately 2.42 acres of City-regulated wetlands on site, the applicant is proposing to impact approximately .28 acre.
 
2.  The impact of .04 acre is located in a low-quality wetland, but it will improve water quality to be discharged in to another wetland offsite.
 
3.  The applicant has reduced potential wetland impact by incorporating a retaining wall in the area of impact for the required vehicle parking.
 
4.  No prudent alternatives exist for constructing the parking, fire lane and detention basin for the development.
 
Conditions:
 
1.  That the applicant receive all applicable MDEQ permits and Oakland County Drain Permits prior to issuance of a Land Improvement Permit.
 
2.  That the applicant provide a detailed soil erosion plan with measures sufficient to ensure ample protection of wetlands areas, prior to Construction Plan Approval.
 
3.  Verification that comments 3f., 3g, and 3h from ASTI's letter of September 19, 2008 are incorporated on the Final Site Plans, prior to Final Approval by Staff.