Request for Final Planned Unit Development (PUD) Site Plan Approval - Brampton Parc Condominiums PUD, a proposed 12-unit residential development on 2.93 acres, located on the east side of John R between Hamlin and School Rds., zoned R-4, One Family Residential, 1459 John R, LLC, Applicant
Body
Resolved, that the Rochester Hills City Council hereby approves the Final Site Plan for Brampton Parc Condominiums PUD, a 12-unit residential development on 2.93 acres, located on the east side of John R between Hamlin and School Rds., zoned R-4, One-Family Residential, Parcel No. 15-24-301-052, 1459 John R, LLC, Applicant, based on plans dated received by the Planning and Economic Development Department on December 22, 2015 with the following findings and subject to the following conditions:
Findings:
1. The site plan and supporting documents demonstrate that all applicable requirements of the Zoning Ordinance, as well as other City ordinances, standards and requirements can be met subject to the conditions noted below.
2. The location and design of driveways providing vehicular ingress to and egress from the site will promote safety and convenience of both vehicular and pedestrian traffic both within the site and on the adjoining street.
3. There will be a satisfactory and harmonious relationship between the development on the site and the existing and prospective development of contiguous land and adjacent neighborhoods.
4. The proposed development does not have an unreasonably detrimental, nor an injurious, effect upon the natural characteristics and features of the parcels being developed and the larger area of which the parcels are a part.
5. The proposed Final Plan promotes the goals and objectives of the Master Plan.
Conditions:
1. Provision of a performance guarantee in the amount of $49,810.00 plus inspection fees, as adjusted if necessary by the City, to ensure the proper installation of trees and landscaping. Such guarantee to be provided by the applicant prior to issuance of a Land Improvement Permit.
2. Payment of $200 per lot into the City’s Tree Fund ($2,400.00).
3. Address all applicable comments from City departments and outside agency review letters, prior to final approval by staff.
4. The existing concept plan zoning site plan, Sheet SP-1.1 shall be removed from the subject plans, prior to final approval by staff.