Title: Request for Approval of the Final Site Plan - Enclaves of Rochester Hills PUD, a proposed 26-unit residential development on 30.5 acres, located on the east side of Rochester Road, north of Tienken, TJ Realvest, LLC, Applicant
Attachments: 1. 042015 Agenda Summary.pdf, 2. Final Site Plans.pdf, 3. Final Eng. Plans.pdf, 4. Final PUD Staff Report 040215.pdf, 5. Review Comments 033115.pdf, 6. Resolution (Draft).pdf
Title
Request for Approval of the Final Site Plan - Enclaves of Rochester Hills PUD, a proposed 26-unit residential development on 30.5 acres, located on the east side of Rochester Road, north of Tienken, TJ Realvest, LLC, Applicant
 
Body
Resolved, that the Rochester Hills City Council hereby approves the Final Site Plan for Enclaves of Rochester Hills PUD, a 26-unit residential development on approximately 30 acres, located on the east side of Rochester Road, north of Tienken, Parcel Nos. 15-02-177-001 and 15-02-102-023, based on plans dated received by the Planning and Economic Development Department on March 2, 2015, TJ Realvest, LLC, Applicant, with the following findings and conditions.
 
Findings:
 
1.  The Site Plan and supporting documents demonstrate that all applicable requirements of the Zoning Ordinance, as well as other City Ordinances, standards and requirements can be met subject to the conditions noted below.
 
2.  The location and design of driveways providing vehicular ingress to and egress from the site will promote safety and convenience of both vehicular and pedestrian traffic both within the site and on adjoining streets.
 
3.  There will be a satisfactory and harmonious relationship between the development on the site and the existing and prospective development of contiguous land and adjacent neighborhoods.
 
4.  The proposed development does not have an unreasonably detrimental, nor an injurious effect upon the natural characteristics and features of the parcels being developed and the larger area of which the parcels are a part.
 
5.  The proposed Final Plan promotes the goals and objectives of the Master Plan.
 
Conditions:
 
1.  Provision of a performance guarantee in the amount of $508,935, as adjusted if necessary by the City, to ensure the proper installation of trees and landscaping.  Such guarantee to be provided by the applicant prior to issuance of a Land Improvement Permit.
 
2.  Address all applicable comments from City departments and outside agency review letters, prior to final approval by Staff.
 
3.  Add a maintenance path along the sanitary sewer line, to be approved by Engineering Staff prior to Construction Plan approval.
 
4. Preconstruction survey of adjacent homesites be done prior to construction to compare to the survey after construction.
 
5. Wetlands be monitored annually and reports submitted to the City for the five years after development.